A custom gear RFQ should define the part, its mating system, operating conditions, acceptance requirements, and purchase quantities. Send a controlled drawing with the twelve information groups below, and identify missing inputs instead of allowing each supplier to make different assumptions. Ask for a written technical scope and exceptions list so engineering and purchasing can compare the offers on the same basis.

1. Decide what the quotation must establish

1.1 Identify the project stage

A concept review, prototype order, and production release need different levels of definition. State which stage the RFQ supports and what decision the quotation will enable. This helps the supplier distinguish a preliminary estimate from an offer against an approved specification.

1.2 Assign responsibility for open design work

Explain whether the supplier is being asked to manufacture a defined gear or help develop its specification. List unresolved engineering tasks and name the person who can approve the resulting decisions. ABEJA's project review overview groups the main inputs around the component, assembly, duty, and acceptance process.

1.3 Establish a common response format

Ask each bidder to return the same categories of information. A short scope table should separate accepted requirements, proposed alternatives, and unresolved questions. It makes differences visible before commercial teams begin comparing prices.

2. Detail 1: Drawing, revision, and supply scope

2.1 Issue one controlled drawing package

Identify the drawing number, revision, units, and issue date in the RFQ. Include related drawings that define the component's required interfaces. If files conflict, identify which document controls and resolve the conflict before requesting a firm quotation.

2.2 Explain the role of the CAD model

State whether the model is a design reference or part of the controlled product definition. Point out simplified teeth, omitted edge details, or other geometry that should not be treated as manufacturing authority. Ask the supplier to flag missing information rather than infer it from a visually complete model.

2.3 Define what is being purchased

Specify a finished gear, gear blank, integrated pinion shaft, matched pair, or larger assembly. List the hardware, documentation, and processing included in the requested scope. This prevents a low component price from being mistaken for the cost of a complete usable set.

3. Detail 2: Mating component and shaft layout

3.1 Identify the exact mate

Provide the mating gear drawing and revision whenever available. If the mate comes from another source, identify the approved component and any measured information needed for review. Do not assume that a familiar gear name establishes interchangeability.

3.2 Show the installed relationship

Include center distance or shaft intersection, shaft angle, bearing positions, and locating surfaces. Add an assembly section where a single part drawing leaves the arrangement unclear. Mark which dimensions are fixed by existing tooling or equipment.

3.3 Define replacement constraints

For a replacement, explain whether one member or the complete pair can be changed. Record the reason for replacement and the condition of the retained parts. This helps engineering distinguish a worn mating system from a simple procurement shortage.

4. Detail 3: Tooth geometry and ratio

4.1 Give the complete geometry definition

State the pitch system, tooth counts, pressure angle, face width, and any specified profile modifications. For standard unshifted spur geometry, module and tooth count establish the reference diameter, not the full finished-part specification. KHK's dimension reference shows why different gear forms require their own calculation basis.

4.2 Add family-specific fields

Helical gearing needs the reference plane, helix angle, and hand as well as its mating information. Bevel gearing needs the defined tooth system and installation references, while worm gearing requires worm and wheel data together. ABEJA's helical gear inputs provide a useful example of these additional fields.

4.3 Flag geometry that remains open

If only the required output motion is known, state that explicitly. Share the ratio, envelope, and operating conditions, then request a proposed geometry for review. Keep that proposal subject to approval rather than silently treating it as the released design.

5. Detail 4: Interfaces, datums, and mounting

5.1 Specify the torque-transfer interface

Define the bore, keyway, spline, clamping feature, or integrated shaft that transfers torque. Include its relevant tolerances and the component with which it must assemble. Check that the interface definition remains consistent across the part and assembly drawings.

5.2 Identify functional datums

Show the surfaces or axes used to locate the part and assess its geometry. Connect tooth-related requirements to those references where the design calls for it. A drawing should make clear how an inspector can set up the component without inventing a datum scheme.

5.3 Show axial location and retention

Include shoulders, spacers, fasteners, and any adjustment arrangement that determines the installed position. For a bevel pair, specify mounting distances from named datums for both members. ABEJA's bevel gear project guidance connects those inputs to contact and assembly review.

6. Detail 5: Torque, speed, and duty cycle

6.1 Provide loads with their durations

List continuous torque, peak torque, and the duration and frequency of each peak. Specify the shaft to which each number applies so input and output values are not mixed. Include the calculation or measurement basis when the duty is still being established.

6.2 Describe motion through the cycle

Give the operating speed range and explain starts, stops, and reversals. For an intermittent machine, include running and resting periods within a normal cycle. A compact time chart can communicate this more clearly than a single maximum-speed entry.

6.3 Separate abnormal events

Describe expected jams, overloads, and emergency-stop conditions separately from normal production. Identify any limiting device or control behavior the design relies on. Ask the technical offer to state which events it includes in its assessment.

7. Detail 6: Material grade and approval rules

7.1 Use an identifiable material designation

Specify the material grade and its governing specification when they are established. A description such as alloy steel leaves substantial room for differing offers. If an equivalent grade may be proposed, state who must approve it and what evidence is required.

7.2 Connect material to the required condition

The material designation and treatment should be reviewed together. KHK's gear materials reference illustrates the range of material and treatment combinations used in gearing. Use that as engineering background, not as evidence that ABEJA offers every listed grade or condition.

7.3 Request the evidence the order needs

Identify the required material records and how they must relate to the delivered batch. Make special traceability or customer-document requirements visible before pricing. The quotation should say which records are included and which require a separate agreement.

8. Detail 7: Treatment, finishing, and final condition

8.1 Define the treatment requirement

Where treatment is specified, include the process requirement and the final characteristics to be verified. State the relevant hardness scale, test location, and case-depth requirement if applicable. When these are undecided, request a proposal rather than inserting a generic value from an unrelated catalog.

8.2 Make the finishing scope explicit

State which surfaces require final finishing and the associated acceptance criteria. If the designer allows different manufacturing routes, ask the supplier to identify its proposed route in the technical offer. This keeps a process preference separate from the finished-part requirement.

8.3 Specify the delivered state

Clarify whether the component arrives fully finished, coated, preserved, or ready for an additional operation. Identify features that must remain available for later machining and who owns that work. ABEJA's spur gear review page can help organize the relationship between tooth geometry and shaft interfaces.

9. Detail 8: Accuracy and inspection characteristics

9.1 Name the standard and edition

An isolated grade number is not a complete accuracy requirement. State the standard designation, edition, and gear characteristics covered by it. Do not assume that the same number under a different standard or historical edition means the same thing.

9.2 Identify the characteristics that matter

Pitch, profile, helix, and runout describe different aspects of gear geometry. KHK's accuracy reference explains these distinctions using its cited standard systems. Select the requirements relevant to the design and confirm the applicable edition with the supplier.

9.3 Agree the reporting scope

Ask which measurements will be reported and how results will be tied to individual parts or lots. Define any customer review required before shipment. A statement that a gear is inspected is less useful than an agreed list of characteristics and acceptance limits.

10. Detail 9: Backlash, contact, and running tests

10.1 Define the backlash measurement

State whether backlash is specified as angular movement or linear clearance and identify the measurement location. Include the mating member and installed settings used for the test. KHK's backlash guide explains why a numerical value needs this context.

10.2 Set the contact-check conditions

If a contact-pattern check is required, describe the setup and acceptance method. Identify the mate, mounting settings, applied load condition, and record to be supplied. Agree who will assess the result so a visual check does not become an undefined approval step.

10.3 Separate component and machine tests

State whether noise, vibration, or positioning must be demonstrated on a component fixture or on the completed machine. Specify the operating conditions and measurement method for each required result. Name the party responsible for providing the fixture, equipment, and final acceptance decision.

11. Detail 10: Environment, lubrication, and holding duty

11.1 Describe the exposure

Include operating and storage temperatures, moisture, debris, cleaning agents, and enclosure conditions. Explain whether exposure is continuous or occasional. The supplier can then identify assumptions that require a material, protection, or maintenance review.

11.2 Identify the lubrication arrangement

Give the proposed lubricant, delivery method, and service interval when known. Flag restrictions such as inaccessible lubrication points or customer-approved lubricant lists. Ask the offer to identify the lubrication assumptions used in its technical assessment.

11.3 Declare any load-holding function

For worm applications, state whether the machine needs to resist back-driving or hold a load after power is removed. Boston Gear's engineering guidance cautions against treating worm gearing as a guaranteed holding device. Define a separate validated holding arrangement where safety requires it.

12. Detail 11: Samples, acceptance, and traceability

12.1 Define what sample approval covers

List the dimensions, material records, functional checks, and documents needed for sample approval. State whether the sample is intended to validate the production process or only the design concept. Require any difference from the proposed production route to be disclosed.

12.2 Connect evidence to the inspected parts

Agree how samples and their reports will be identified. The reviewer should be able to connect each relevant result to the drawing revision and delivered items. Include the record format and any required review milestone in the quotation request.

12.3 Define changes after approval

State which changes require notification or renewed approval. Include the handling of revised drawings, approved deviations, and subsequent orders. This gives purchasing a clear reference when production continues beyond the first accepted batch.

13. Detail 12: Quantities, dates, and commercial scope

13.1 Distinguish samples from forecast demand

Provide the sample quantity, initial production quantity, and expected repeat-order pattern separately. Label forecasts as forecasts and distinguish them from a committed order. Ask the supplier to identify the quantity assumptions behind its price.

13.2 Tie dates to milestones

State the requested quotation date, sample need date, and intended production start. Ask when the supplier's lead-time estimate begins and which approvals it depends on. This avoids comparing delivery estimates that start from different events.

13.3 Request the complete cost basis

Ask for tooling, engineering, samples, production parts, inspection, packaging, and delivery to be identified where applicable. Include the quotation currency, validity, and requested delivery basis. Seek written clarification of minimum order quantities and repeat-order conditions instead of assuming them.

14. Copy this custom gear RFQ template

14.1 Complete the twelve input groups

The table below can be copied into a sourcing request. It is an original buyer worksheet, with fields to complete for the actual project. Mark unresolved information as open and assign a responsible person rather than leaving its status ambiguous.

Custom gear RFQ worksheet
Input groupInformation to complete
1. Drawing and scopePart number; revision; units; controlled files; component, pair, or assembly; project stage.
2. Mate and layoutMating drawing; shaft arrangement; center distance or shaft angle; fixed packaging constraints.
3. Tooth geometryGear family; module or DP; reference plane; pressure angle; tooth counts; ratio; family-specific geometry.
4. InterfacesBore or shaft; keyway or spline; fits; datums; mounting distances; retention.
5. Operating dutyTorque and speed by shaft; peak duration; duty cycle; starts; reversals; exceptional loads.
6. MaterialGrade and specification; allowed alternatives; approval owner; required material records.
7. Final conditionTreatment; hardness and test location; case depth if required; finishing; coating or preservation.
8. AccuracyStandard and edition; defined characteristics; tolerances; inspection and reporting scope.
9. Functional checksBacklash definition and conditions; contact check; noise or positioning test; responsibility.
10. EnvironmentTemperature; exposure; lubricant; maintenance; back-driving or holding requirements.
11. AcceptanceSample approval criteria; required reports; identification; change notification; production release.
12. Purchase planSample and production quantities; forecast; requested milestones; cost breakdown; delivery basis.

14.2 Use a short message to introduce the files

The covering message should explain the requested decision and direct the supplier to the controlled information. It does not need to repeat every drawing dimension. The editable message below gives a starting structure for the inquiry.

Please quote the attached gear component or set against the identified drawing revision and completed RFQ worksheet.
Please return your proposed supply scope, technical exceptions, open questions, sample and production pricing, tooling or engineering charges, inspection deliverables, and estimated lead-time basis.
Please identify any requirement that needs engineering review before a firm quotation or production release.

14.3 Attach only the relevant controlled package

Include a file list so the recipient can confirm what was received. Identify superseded documents clearly if they must remain in the discussion for reference. Where confidentiality restrictions apply, arrange the agreed handling before transmitting restricted drawings.

15. Compare quotations and close the open issues

15.1 Review technical differences first

Check that each offer uses the same revision, mating assumptions, material condition, and acceptance scope. Record exceptions beside the affected requirement. Ask engineering to approve or reject those differences before purchasing treats the offers as equivalent.

A compact quotation comparison record
Comparison itemRecord for each supplier
Technical scopeAccepted specification and every exception.
Commercial scopeRecurring price, one-time charges, quantities, and delivery basis.
EvidenceSample checks, reports, traceability, and approval responsibilities.
ScheduleStarting event, dependencies, and quoted milestones.
Unresolved itemsOwner, required answer, and decision date.

15.2 Release a documented baseline

Once the proposal is acceptable, consolidate the agreed requirements and deviations. Reference that baseline in the purchase order and sample approval process. Keep later changes identifiable so repeat orders do not depend on an old email assumption.

15.3 Start an ABEJA project discussion

Use ABEJA Gears' inquiry page to explain the component and request a review of the quotation requirements. Bring the drawing revision, mating information, duty, quantities, and unresolved questions into that discussion. Confirm the available manufacturing scope, documentation, and commercial terms in the resulting offer.

16. Frequently asked questions

16.1 Can I request a quote without a complete drawing?

Yes, an initial inquiry can begin with the available measurements, photographs, and application information. State that the specification is incomplete and ask what work is needed to define it. Treat any preliminary price according to its stated assumptions until the technical requirements are agreed.

16.2 Why can two custom gear quotes differ so much?

The offers may include different materials, treatments, inspection records, quantities, or engineering work. They may also rely on different assumptions about the mating system and sample approval. Compare the written scope before concluding that the difference is simply the supplier's unit margin.

16.3 Does a higher accuracy grade remove the need for a test?

A component accuracy requirement does not replace every assembly or operating check. The relevant acceptance process depends on what the drawing and machine specification require. Keep gear inspection and functional validation connected to their distinct purposes in the order.

2 Responses